Holman Tank Demolition and Pressure Zone 3/5 Water System Intertie Improvements

3 Documents in Project

Summary

SCH Number
2012102012
Lead Agency
City of Fortuna
Document Title
Holman Tank Demolition and Pressure Zone 3/5 Water System Intertie Improvements
Document Type
NOD - Notice of Determination
Received
Posted
4/25/2013
Present Land Use
Residential Single Family
Document Description
1) New pipeline connecting Pressure Zones 3 and 5 including pipeline installation by trenching and directional drilling; pressure reducing station, interconnections with existing piping and installation of individual pressure reducing valves on homes as required. 2) Removal of existing pump and installation of a new pump to augment fire flow, along with a standby generator, new controls and site improvements. 3) Demolition and removal of the Holman tank, tank foundation and associated appurtenances.

Contact Information

Name
Liz Shorey
Agency Name
City of Fortuna
Contact Types
Lead/Public Agency

Location

Cities
Fortuna
Counties
Humboldt
Cross Streets
Home Avenue/north of P Street
Zip
95540
Total Acres
5
Parcel #
040-092-033; 200-071-01, 081-15-082
State Highways
Hwy 101
Railways
Northwestern Pacific
Airports
No
Schools
Fortuna MS, Senior
Waterways
Eel River
Township
3N
Range
1W
Section
26/35
Base
HB&M

Notice of Determination

Approving Agency
City of Fortuna
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print