State Route 150 Slope Stabilization and Erosion Control Project

5 Documents in Project

Summary

SCH Number
2012071089
Lead Agency
California Department of Transportation, District 7
Document Title
State Route 150 Slope Stabilization and Erosion Control Project
Document Type
NOD - Notice of Determination
Received
Posted
2/25/2013
Present Land Use
Transportation - Unincorporated Ventura County
Document Description
DFW is intending to execute a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code (#1600-2012-0083-R5) to the project applicant, Caltrans. The Permittee proposes to stabilize the slope at two locations on SR-150. Project Site 1 (PS1) is located along Santa Paula Creek and Project Site 2 (PS2) is located along Sisar Creek. Impacts resulting from Implementation based on the provided Project description as stated herein, at PS1 shall not exceed 0.386-acre (0.275-acre Temporary + 0.111-acre Permanent) as the result of the removal of six coast live oaks (Quercus agrifolia), three California sycamores (Platanus Racemosa), and at PS2 one toyon (Heteromeles arbutifolia) for installation of the piles and retaining wall footing. In addition to restoration of areas temporarily impacted mitigation shall include the restoration of an addition 0.55 acre of riparian corridor within the Santa Paula Creek watershed.

Contact Information

Name
Jamie Jackson
Agency Name
Department of Fish and Wildlife (DFW)
Contact Types
Lead/Public Agency

Location

Cities
Santa Paula
Counties
Ventura
Cross Streets
SR 150 and Mistletoe Road (near Steckel Park)
Zip
93060
State Highways
Hwy 150
Schools
Thomas Aquinas College
Waterways
Sisar and Santa Paula Creeks

Notice of Determination

Approving Agency
DFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print