Ranchero Road Improvement Project
5 Documents in Project
Summary
SCH Number
2012061058
Lead Agency
City of Hesperia
Document Title
Ranchero Road Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
6/20/2013
Present Land Use
Tranportation/Residential/Commercial/Industrial/Institutional/Open Space
Document Description
The City of Hesperia (City) in cooperation with the County of San Bernardino (County) proposes improvements to a 5.5-mile stretch of Ranchero Road generally, from on the west approximately 2,200 feet east of Mariposa Road to Seventh Avenue on the east. The proposed project will involve widening existing two-lane segments of Ranchero Road to four lanes, with a 12-ft painted two-way left-turn median and 6-ft shoulders in both directions. On-street parking will not be allowed. Shoulder width and other dimensions would vary, depending upon whether the subject roadway segment is located in City or County jurisdiction. The total estimated roadway right-of-way width is anticipated to range between 120-ft and 140-ft. The at-grade Union Pacific Railroad crossing will be designed for its ultimate width of 92-ft. In addition to widening the existing two-lane roadway road segments to four lanes, the project includes asphalt concrete pavement (AC) overlay in some areas, culvert extensions, and stormwater facilities. The proposed project would require AC removal and replacement along existing sections of Ranchero Road that have not already been widened to four lanes.
Contact Information
Name
Scott Priester
Agency Name
City of Hesperia
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Hesperia
Counties
San Bernardino
Cross Streets
From east Ranchero Rd. & Mariposa Rd. to Intersection of Ranchero Rd. and 7th Ave.
Zip
92344
Total Acres
95
Parcel #
NA
State Highways
I-15 and US-395
Railways
UPPR and BNSF
Airports
Hesperia
Schools
Multiple
Waterways
Multiple
Township
4N
Range
5W
Section
31/32
Base
SBB&M
Notice of Determination
Approving Agency
City of Hesperia
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes