Wastewater Flow Re-Routing Project - Change to Proposed Alignment
10 Documents in Project
Summary
SCH Number
2012041010
Lead Agency
Templeton Community Services District
Document Title
Wastewater Flow Re-Routing Project - Change to Proposed Alignment
Document Type
NOD - Notice of Determination
Received
Posted
11/10/2015
Present Land Use
Unincorporated lands are Rural Lands and Agricultural designations
Document Description
The new pipeline alignment would run along approximately 1.5 miles within existing road rights-of-way and streets. The northern end of the new pipeline alignment begins approximately 1000 ft south of the HW 101 overpass where the project force main enters North Main Street, and then travels south along N. Main Street to Old County Road. The pipeline will then follow Old Country Road south to the intersection of Las Tablas Rd. The route will continue along Las Tablas Rd and travel under HW 101. The pipeline will turn south at Bennett Way and terminate at the existing Westside Lift Station. The pipeline will be within rights-of-way of existing roadways. It will pass in front of commercial retail, residential suburban, office professional, recreation, commercial service, residential single family, and residential multi family land use designations adjacent to the roadway. The revised alignment considered in the Subsequent MND and IES includes three creek under bore crossings: two under North Main St and Road Creek and one under-bore crossing where Las Tablas crosses Toad Creek; and one boring under US HW 101 at Las Tablas Rd.
Contact Information
Name
Tina Meyer
Agency Name
Templeton Community Services D
Contact Types
Lead/Public Agency
Phone
Location
Cities
Paso Robles
Counties
San Luis Obispo
Cross Streets
roughly parallel the Salnas River/UPRR
Zip
93449
Parcel #
Public Rights of Way
State Highways
Hwy 101
Railways
UPRR
Waterways
Salinas River
Other Location Info
City/Nearest Community: Templeton
Notice of Determination
Approving Agency
Templeton Community Services District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.