Cabin Creek Biomass Facility Project (at Eastern Regional MRF and Transfer Station site)

6 Documents in Project

Summary

SCH Number
2011122032
Lead Agency
Placer County
Document Title
Cabin Creek Biomass Facility Project (at Eastern Regional MRF and Transfer Station site)
Document Type
NOD - Notice of Determination
Received
Posted
5/7/2013
Present Land Use
Placer County General Plan: Agricultural/Timberland - 80 Acre Minimum; Zoning: forestry-special purpose (FOR-SP)
Document Description
The project proposes to construct a two-megawatt (MW) wood-to-energy biomass facility that would use a gasification technology at the Eastern Regional Materials Recovery Facility (MRF) and Landfill. The proposed project would include construction of an approximately 11,000 square-foot, two-story structure to house the power generating and emission control equipment, an approximately one-acre material storage area including a 7,000 square-foot open aired pole barn structure, and additional onsite improvements to support operations at the facility.

Contact Information

Name
Maywan Krach
Agency Name
Placer County Community Development Resource Agency
Contact Types
Lead/Public Agency

Location

Cities
Truckee
Counties
Placer
Cross Streets
SR 89/Cabin Creek Road
Zip
96161
Parcel #
080-070-016
State Highways
SR 89
Waterways
Truckee River
Township
17N
Range
16E
Section
28
Base
MDB&M

Notice of Determination

Approving Agency
Placer County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print