Salem Lutheran Church and School - General Plan Amendment No. 2014-02, Zone Change No. 1259-11, Specific Plan No. SPLAN-0002, Design Review Committee No. 4538-1
3 Documents in Project
Summary
SCH Number
2011101046
Lead Agency
City of Orange
Document Title
Salem Lutheran Church and School - General Plan Amendment No. 2014-02, Zone Change No. 1259-11, Specific Plan No. SPLAN-0002, Design Review Committee No. 4538-1
Document Type
NOD - Notice of Determination
Received
Posted
3/20/2015
Present Land Use
Existing Church and School/R-1-40 (Single-Family Residential 40,000 sq. ft)/Estate Low Density Residential 0-2 du/ac
Document Description
The applicant is proposing the Salem Lutheran Church and School Specific Plan, which provides for a redesign of the church and school campus with a new approximately 23,000 square foot worship center that includes a 590 seat sanctuary, conference/meetings rooms, the sacristy, offices, choir/music rooms, storage, childcare, and other ancillary/administrative rooms. In order to accommodate the new worship center, the existing 3,262 square foot sanctuary building, and the existing 3,040 square foot preschool building will be demolished. Further, the existing on-site vacant structure (referred to as the "Fowler House" in the community) will be demolished, in order to accommodate a new preschool building. The new preschool building is proposed to be 7,505 square feet. Seven classrooms of approximately 525 square feet are proposed. Existing on-site infrastructure related to storm water, water quality management, vehicle circulation, and parking design are also part of the redesign. As part of this proposed project, a General Plan Amendment, Zone Change, and environmental review are required.
Contact Information
Name
Robert Garcia
Agency Name
City of Orange - Community Development Department
Contact Types
Lead/Public Agency
Phone
Location
Cities
Orange
Counties
Orange
Cross Streets
6500 East Santiago Canyon road west of Orange Park Boulevaard
Zip
92869
Parcel #
379-451-09, 11, 12, 13
Notice of Determination
Approving Agency
City of Orange
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.