City of Fresno Raw Water Pipeline Project (California Endangered Species Act Incidental Take Permit No. 2081-2014-056-04 (ITP) Major Amendment No. 1)

11 Documents in Project

Summary

SCH Number
2011081073
Lead Agency
City of Fresno
Document Title
City of Fresno Raw Water Pipeline Project (California Endangered Species Act Incidental Take Permit No. 2081-2014-056-04 (ITP) Major Amendment No. 1)
Document Type
NOD - Notice of Determination
Received
Posted
10/28/2015
Present Land Use
Present: agriculture, rural residential, public facilities (SWTP). Fresno County GP: Agriculture, Rural Residential
Document Description
The Project will involve the construction of an underground raw water pipeline which will convey raw (untreated) surface water from the existing Friant-Kern Canal to the existing City of Fresno Surface Water Treatment Facility where it will be treated for domestic use. The Project will result in impacts to 12.56 acres of California tiger salamander habitat including temporary impacts to 9.80 acres of upland habitat for the species, the permanent loss of 2.21 acres of upland habitat for the species, and the potential loss of up to 0.55 acres (two pools) of potential breeding habitat for the species. The Project is expected to result in incidental take of California tiger salamander, which is designated as a threatened species under the California Endangered Species Act. The ITP referenced above as reissued by CDFW authorizes incidental take of species listed under CESA that may occur as a result of Project implementation.

Contact Information

Name
Steve Hulbert
Agency Name
CDFW Central Region
Contact Types
Lead/Public Agency

Location

Cities
Clovis, Fresno
Counties
Fresno
Cross Streets
Auberry Rd., E. Copper Avenue, N. Willow Avenue, Foothill Rd.
Zip
93611
Total Acres
126.5
Parcel #
multiple
State Highways
Hwy 41
Railways
No
Airports
No
Schools
multiple
Waterways
Big Dry Creek Diversion Channel, Friant-Kern Canal
Township
12S
Range
21,20E
Section
multip

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print