Idyllwild Water District (District); Tertiary Recycled Water System (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-7808-110
3 Documents in Project
Summary
SCH Number
2010081032
Lead Agency
Idyllwild Water District
Document Title
Idyllwild Water District (District); Tertiary Recycled Water System (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-7808-110
Document Type
NOD - Notice of Determination
Received
Posted
4/29/2015
Present Land Use
Rural/Vacant -Riverside Extended Mountain Area Plan
Document Description
The pipeline route would be located partially within the public right-of-way and partially through private property, travel on the north side of Strawberry Creek and terminate at the water storage tank in the Idyllwild Pines Campground. The pipeline would begin at the WWTP, travel onto Tollgate Road, Delano Drive, cross utility easements parallel to and on the north side of Strawberry Creek, goes northeast onto Pine Crest Avenue, and connect to the water storage tank in the Idyllwild Pines Campground.
Contact Information
Name
Carina Gaytan
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
Riverside
Cross Streets
Lower Pine Crest Drive/State Highway 243
Zip
92549
Total Acres
150
Parcel #
557-120-002
State Highways
Hwy 243
Township
5S
Range
2W
Section
14
Base
SBB&M
Other Location Info
City/Nearest Community: Idyllwild
Notice of Determination
Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.