Hesperie Subregional Wastewater Reclamation Plant (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-4807-110

7 Documents in Project

Summary

SCH Number
2010051087
Lead Agency
Victor Valley Wastewater Reclamation Authority
Document Title
Hesperie Subregional Wastewater Reclamation Plant (Project); Clean Water State Revolving Fund (CWSRF) No. C-06-4807-110
Document Type
NOD - Notice of Determination
Received
Posted
6/4/2014
Document Description
The Project will consist of constructing the Hesperia Sub regional WRP with a mechanical 1.0 Million gallon per day treatment capacity, constructing percolation ponds, constructing a new Hesperia Raw Sewage lift station surrounded by a 6-foot high block wall, constructing approximately 730 feet of 18-inch gravity interceptor pipeline from the new Hesperia Raw Sewage lift station to the connection with an existing 12-inch sanitary sewer pipeline, constructing approximately 2,265 feet of 12-inch force main from the Hesperia Raw Sewage lift station to the Hesperia WRP, and constructing a recycled water pump station.

Contact Information

Name
Christine Day
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Apple Valley, Hesperia
Counties
San Bernardino
Cross Streets
Bear Valley Road / Hesperia Road / I-15
Zip
92345
Total Acres
~60
State Highways
I-15
Railways
BNSF
Airports
Apple Valley Airport
Schools
several
Waterways
Mojave River
Township
4-6N
Range
3,4W
Section
many
Base
SBB&M

Notice of Determination

Approving Agency
State Water Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.