Baker Water Treatment Plant

7 Documents in Project

Summary

SCH Number
2010051055
Lead Agency
Irvine Ranch Water District
Document Title
Baker Water Treatment Plant
Document Type
NOD - Notice of Determination
Received
Posted
2/11/2020
Document Description
Irvine Ranch Water District (IRWD) has prepared Addendum No. 4 to the Final Environmental Impact Report (EIR) for the Baker Water Treatment Plant (WTP) Project. The Baker WTP original design included the construction of an outfall system that was designed to safely discharge emergency releases from the Baker WTP and storm runoff from the adjoining Serrano Summit residential neighborhood into a small existing unnamed tributary to Serrano Creek. The Project proposes to implement repairs and improvements to the Baker WTP outfall system below the constructed concrete energy dissipater to repair existing erosion and stabilize the tributary slopes. Repair and modifications include the construction of five, 5-foot drop structures constructed of soil cement; installation of riprap bank protection downstream of the soil cement; and installation of geo-grid within the banks to increase stability in order to convey discharge and protect the banks of the Unnamed Tributary from future erosion.

Contact Information

Name
Jo Ann Corey
Agency Name
Irvine Ranch Water District
Contact Types
Lead/Public Agency

Name
Agency Name
Irvine Ranch Water District
Contact Types
Project Applicant

Location

Cities
Lake Forest
Counties
Orange

Notice of Determination

Approving Agency
Irvine Ranch Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search Print