Construction and Operation of the Baker Water Treatment Plant

7 Documents in Project

Summary

SCH Number
2010051055
Lead Agency
Irvine Ranch Water District
Document Title
Construction and Operation of the Baker Water Treatment Plant
Document Type
NOD - Notice of Determination
Received
Posted
10/27/2016
Present Land Use
Public Facilities; Residential; Open Space Park
Document Description
SWRCB, as the responsible agency, will be issuing a water supply permit. The Irvine Ranch Water District proposed project includes construction and operation of a 28 million gallon per day water treatment plant that will use microfiltration membranes and ultraviolet disinfection to treat water from the Lake Matthews and Irvine Lake sources to provide water to district customers and 4 other agencies (El Toro Water District, Mouton Niguel Water District, Santa Margarita Water District, and Trabuco Canyon Water District) to be used during emergency conditions or during scheduled maintenance of the Metropolitan Water District of Southern California's Diemer Treatment Plant, to improve water supply reliability. The project will also include a new off-site pump station near Peter's Canyon Reservoir, a meter exchange and pipeline replacement, anew sewer pipeline for non-reclaimable wastewater, new pipelines to convey treated water, a residuals handling facility that would allow processing on site, and two new electrical conduit alignments.

Contact Information

Name
Oliver Pacifico
Agency Name
SWRCB
Contact Types
Lead/Public Agency

Location

Cities
Orange
Counties
Orange
Cross Streets
Wisteria Lane and Palmwood Drive, Lake Forest
Zip
92630
Total Acres
8
State Highways
Hwy 241
Railways
BNSF/Metrolink
Airports
El Toro MCAS (decommissioned)
Schools
Lake Forest Montessori, Fullbright Montessori, Rancho Canada ES
Waterways
Serrano Creek, Peters Canyon Reservoir
Other Location Info
City/Nearest Community: Orange, Lake Forest

Notice of Determination

Approving Agency
SWRCB
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print