Cameron Ridge Wind Energy Project, California Endangered Species Act Incidental Take Permit (ITP) No. 2081-2011-031-04, Minor Amendment 3

11 Documents in Project

Summary

SCH Number
2010031109
Lead Agency
Kern County
Document Title
Cameron Ridge Wind Energy Project, California Endangered Species Act Incidental Take Permit (ITP) No. 2081-2011-031-04, Minor Amendment 3
Document Type
NOD - Notice of Determination
Received
Posted
4/25/2014
Present Land Use
Vacant/A (Exclusive)
Document Description
This proposed Project involves a minor amendment to the ITP referenced above to extend the deadline to permanently protect the Habitat Management (HM) Lands from January 5, 2014 to January 5, 2015. No other changes were made to the ITP. There is no change to the Project description or other ITP conditions. The ITP as amended, authorizes take of Bakersfield cactus (Opuntia basilaris var. treleasei), species designated as endangered under CESA. CDFW issued the original ITP, and approved Minor Amendment Nos. 1 through 3 as a responsible agency under the California Environmental Quality Act (CEQA) relying on the mitigated negative declarations prepared for the Project as approved by the lead agency, County of Kern.

Contact Information

Name
Julie Vance
Agency Name
California Department of Fish and Game, Central Region
Contact Types
Lead/Public Agency

Location

Cities
Mojave
Counties
Kern
Cross Streets
Oak Creek Rd.
Total Acres
69
Parcel #
237-510-02, 13; 237-520-06
Township
11N
Range
14W
Section
11
Base
SBB&M

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print