East County Substation/Tule Wind/Energia Sierra Juarez Gen-Tie Projects

11 Documents in Project

Summary

SCH Number
2009121079
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
East County Substation/Tule Wind/Energia Sierra Juarez Gen-Tie Projects
Document Type
NOD - Notice of Determination
Received
Posted
10/14/2016
Present Land Use
Undeveloped Z: General Rural, Open Space, Specific Plan, Agriculture, Indian Reservation GPD: Multiple Rural Use (1 DU/4, 8, 20 AC), Public/Semi-Public Lands, Specific Plan Area, General Agriculture, Indian Reservation
Document Description
Construction, operation, maintenance, and decommissioning of a new wind energy facility on State-owned school lands consisting of up to seven wind turbines with 1.5 to 3.0 megawatts capacity each. The State Lands Commission action is an approval of a 40-year General Lease - Industrial Use through Oct. 12, 2056.

Contact Information

Name
Jim Porter
Agency Name
CA State Lands Commission
Contact Types
Lead/Public Agency

Location

Counties
San Diego
Cross Streets
Old Highway 80, Carrizo Gorge Road, Tule Jim Lane, Highway 94, McCain Valley Rd, Ribbonwood Rd
Zip
Multiple
Parcel #
Multiple
State Highways
I-8, SR-94
Railways
San Diego and Arizona Eastern
Airports
Jacumba
Schools
Clover Flat Elementary, Jacumba Elementary
Waterways
Multiple
Township
Multip
Section
Multip
Base
Multiple
Other Location Info
City/Nearest Community: Jacumba/Boulevard
Other Information
Schools: Mountain Empire Unified School District

Notice of Determination

Approving Agency
CA State LAnds Commission
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.