Mustafa Minor Subdivision; Tentative Parcel Map; TPM 20811RPL/ER04-02-007
2 Documents in Project
Summary
SCH Number
2009061078
Lead Agency
San Diego County
Document Title
Mustafa Minor Subdivision; Tentative Parcel Map; TPM 20811RPL/ER04-02-007
Document Type
NOD - Notice of Determination
Received
Posted
8/12/2009
Document Description
This project proposes to subdivide 16.37 gross acres into 4 parcels and a Designated Remainder Parcel, which range in size from 2.16 acres net to 4.12 acres net. The project site is located on the corner of Circle R Drive and Circle R Lane, in the Valley Center Community Planning Group, within unincorporated San Diego County. The site is subject to the General Plan Regional Category Estate Development Area and Land Use Designation 17 Estate Residential. Zoning for the site is A70, Limited Agriculture. The site contains an existing single family residence that would be retained. Access would be provided by a private road connecting to Circle R Drive. The project would be served by on-site septic systems and imported water from the Valley Center Municipal Water District. No extension of sewer or water utilities will be required by the project. Earthwork will consist of cut and fill of ~12,655 cubic yards of material.
Contact Information
Name
Marisa Smith
Agency Name
San Diego County
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Counties
San Diego
Cross Streets
Corner of Circle R Lane and Circle R Drive
Zip
92026
Total Acres
16.4
Parcel #
129-390-17-00
Schools
Valley Center HS & ES
Waterways
Keys Creek
Township
10S
Range
2W
Section
29
Other Location Info
City/Nearest Community: Valley Center
Notice of Determination
Approving Agency
San Diego County
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A