Emerald Bay Community Association Safety Improvement Project
Document Type
NOD - Notice of Determination
Received
Posted
11/12/2010
Present Land Use
GP: 1B-Suburban Residential (Orange County) / 5.2-Recreation (Emerald Bay Local Coastal Program)
Document Description
The project proposes to improve the Emerald Bay Community main entrance at PCH and Shamrock Road. The improvements consist of widening Shamrock Road ranging from 25-30 ft, the relocation and reconstruction of the existing guardhouse which will be relocated ~40 ft north of the existing location, grading of Shamrock Road and the adjacent slope to accommodate the widening of the road and landscaping. A traffic signal, a raised median at the intersection of PCH and Shamrock Road and street striping and signage will be constructed within the Caltrans right-of-way. A draft MND was originally circulated for public review on June 3, 2009. A number of refinements to the project have been made and the MND was recirculated on July 16th, 2010. Refinements addressed in the RMND related to the proposed construction improvements within the Caltrans right-of-way on PCH.
Contact Information
Name
Channary Leng
Agency Name
Orange County
Contact Types
Lead/Public Agency
Phone
Location
Cities
Laguna Beach
Counties
Orange
Cross Streets
Pacific Coast Highway / Shamrock Rd
Total Acres
~.251
State Highways
Hwy 1 (PCH)
Railways
No
Airports
No
Schools
Laguna Beach HS,Thurston MS,Top of the World ES
Waterways
Pacific Ocean
Notice of Determination
Approving Agency
County of Orange
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes