East Campus Infrastructure Improvement Phase 2
2 Documents in Project
Summary
SCH Number
2009041007
Lead Agency
University of California, Riverside
Document Title
East Campus Infrastructure Improvement Phase 2
Document Type
NOD - Notice of Determination
Received
Posted
11/29/2010
Present Land Use
2005 LRDP LU: Academics; Athletics and Recreation; Open Space; Open Space Reserve; Campus Support; Parking
Document Description
The proposed Project would address a series of critical utility requirements by: improving existing 12kV electrical services to support short- and long-term building growth and provide reliable and increased capacity to four existing buildings; increasing heating capacity to the East Campus by installing one 50,000 pound per hour boiler and two 100,000 pound per hour deaerators; enhancing chilled water capacity by installing a 2,000-ton chiller and an additional 2.7 million gallon TES Tank and extending utility distribution service to a currently undeveloped area north of North Campus Drive, including potable and domestic water, steam, chilled water, sanitary sewer, and 12kV electrical systems.
Contact Information
Name
Tricia D. Thrasher
Agency Name
University of California, Riverside
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Riverside
Counties
Riverside
Parcel #
253-100-002; 251-180-005
State Highways
SR 60
Railways
AT&SF/RCTC Line
Schools
3 ES, 1 MS, 1 HS
Township
2S
Range
4W
Section
N1/2
Base
SBB&M
Other Information
Section: 29A; S1/2 20
Notice of Determination
Approving Agency
University of California, Riverside
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes