Bodega Bay Beach Erosion Emergency Repair Project
2 Documents in Project
Summary
SCH Number
2009032026
Lead Agency
Sonoma County
Document Title
Bodega Bay Beach Erosion Emergency Repair Project
Document Type
NOD - Notice of Determination
Received
Posted
5/11/2009
Document Description
The project includes a total of five projects included in the Federal Emergency Management Agency's (FEMA) program associated with the 2006-2006 New Year Storm Event. These projects are included in the Governor's Office of Emergency Services Declaration #2006-01, issuead February 03, 2006. This Declaration corresponds with Presidential Declaration DR-1928-CA. FEMA has Categorically Excluded these projects from the need to conduct environmental review under the national Enviromental Policy Act (NEPA).
The project essentially involves replacement of rock rip-rap and engineered backfill along embankments of the facilities. Replacement of timbersm crossbeams, and pilings will be made at the southern breakwater at the Sport Fishing Center.
Contact Information
Name
Michelle Julene
Agency Name
Sonoma County
Contact Types
Lead/Public Agency
Phone
Location
Counties
Sonoma
Cross Streets
various
Zip
94923
Total Acres
1
Parcel #
Sec No 1
State Highways
1
Waterways
Bodega Bay
Township
6N
Range
11W
Section
26
Base
MDB&M
Other Location Info
City/Nearest Community: Bodega Bay
Notice of Determination
Approving Agency
Sonoma County
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A