Villa Verona STEP Sewer System Replacement - Phase 1

3 Documents in Project

Summary

SCH Number
2009012073
Lead Agency
Lake Oroville Area Public Utility District (LOAPUD)
Document Title
Villa Verona STEP Sewer System Replacement - Phase 1
Document Type
NOD - Notice of Determination
Received
Posted
4/27/2009
Present Land Use
AR-1 (Agricultural/Residential)
Document Description
The project involves the construction of new gravity sewer pipelines, manholes, and services to replace existing Septic Tank Effluent Pump (STEP) system pumps, tanks, and pressure pipelines. The proposed project includes the installation of 2,400 lineal feet of 15-inch sewer pipeline, 4,000 lineal feet of 8" sewer pipeline, and approximately 45 service laterals with a total length of approximately 1,050 feet, to improve hydraulics, eliminate surcharging, and reduce sewage pumping. The project will also include approximately 30 new manholes. Construction of the project will require the acquisition of a number of easements crossing private properties.

Contact Information

Name
Alan Brown
Agency Name
Lake Oroville Area Public Utility District
Contact Types
Lead/Public Agency

Location

Cities
Oroville
Counties
Butte
Cross Streets
Lower Wyandotte Rd, Oak Knoll Dr, V-6 Rd, Oro Garden Ranch Road, Claremont Rd
Zip
95966
Total Acres
1.26
Parcel #
various
State Highways
70
Railways
CPRR
Schools
Las Plumas, Golden Hill
Waterways
Feather River
Township
19N
Range
4E
Section
21
Base
MDM

Notice of Determination

Approving Agency
Lake Oroville Area Public Utility Dist.
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes