Sky Mountain Reservoir No. 4605 and Pipeline Project

4 Documents in Project

Summary

SCH Number
2009011024
Lead Agency
Coachella Valley Water District
Document Title
Sky Mountain Reservoir No. 4605 and Pipeline Project
Document Type
NOD - Notice of Determination
Received
Posted
8/26/2009
Present Land Use
Medium Density Residential
Document Description
CVWD proposes the construction of two, 10 million gallon reservoirs and an associated water conveyance pipeline. If the reservoirs are constructed of concrete, they will be partially buried with a base elevation of 435 ft. A driveway will be constructed within the site boundary and will be placed one foot inside the property line. The proposed underground pipeline will consist of ~14,400 linear ft of 36 inch diameter pipe that will begin at the reservoir site and ultimately connect to an existing pipeline south of the I-10, just north of the Ramon Road/Bob Hope Drive intersection. The pipeline construction easement will be 100 ft wide, with 50 ft on either side of the proposed pipeline.

Contact Information

Name
Luke Stowe
Agency Name
Coachella Valley Water District
Contact Types
Lead/Public Agency

Location

Counties
Riverside
Cross Streets
Ramon Rd/I-10
Zip
92276
Total Acres
~13
Parcel #
Var
State Highways
I-10
Railways
UPRR
Township
4S
Range
6E
Section
18
Base
SBB&M
Other Location Info
City/Nearest Community: Thousand Palms

Notice of Determination

Approving Agency
Board of Directors of the Coachella Valley Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A