Napa Pipe

8 Documents in Project

Summary

SCH Number
2008122111
Lead Agency
Napa County
Document Title
Napa Pipe
Document Type
NOD - Notice of Determination
Received
Posted
12/14/2015
Present Land Use
Study Area/Industrial (I:AC)
Document Description
The project is limited to: 1) installing a new 54-ft wide, 89 ft long clear span bridge made of pre-cast concrete support with a 9in poured in place concrete slab top; 2) installing two new poured-in-place concrete bridge abutments; 3) installing four poured-in-place concrete wing walls, two on each abutment; and 4) implementing a riparian enhancement plan to be prepared to compensate for permanent impacts to approximately 6,100 sf of existing riparian and associated vegetation, including buckeye, ceonothus, and coyote brush. CDFW is executing a lake and streambed alteration agreement no. 1600-2015-0115-3 pursuant to section 1602 of the fish and game code to the project applicant, Richard Thomasser, Napa County Department of Public Works.

Contact Information

Name
Suzanne Gilmore
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Napa
Counties
Napa
Cross Streets
Kaiser Road and Syar Industrial Way
Zip
94558
Total Acres
154
Parcel #
046412005 & 046400030
State Highways
Hwy 29, 221
Railways
UPRR
Airports
Napa County
Schools
Napa Valley College
Waterways
Napa River

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print