Jess S. Jackson and Barbara R. Banke

3 Documents in Project

Summary

SCH Number
2008092055
Lead Agency
Sonoma County
Document Title
Jess S. Jackson and Barbara R. Banke
Document Type
NOD - Notice of Determination
Received
Posted
4/1/2009
Document Description
Request is for a (1) a lot line adjustment between two parcels 641.3 acres (Lot A) and 15.2 acres (Lot B) in size, resulting in tow parcels 548.7 acres and 107.6 acres in size, resulting in (2) the modification (enlarge and reduce) of two existing Agricultural Preserve areas (2-400 and 1-267); to allow for (3) the rescission and replacement of two existing Williamson Act contracts (Type I and II) with two new Type I Williamson Act contracts on resultant Lot A and resultant Lot B, and a new Type II Williamson Act contract on the applicants' adjacent parcel APN: 120-040-007 (not part of the LLA or UP/DRC requests), and (4) for a Use permit and design review for a winery on resultant Lot B of 107.6 acres for a winery with an annual maximum production capacity of 5,000 cases to include a public tasting room with retail sales, and a maximum of four special events per year with a maximum capacity of 200 guests per event, and the reduced front yard setback of 160 ft from the centerline of Highway 128 for the new tasting room.

Contact Information

Name
Traci Tesconi
Agency Name
Sonoma County Permit and Resource
Contact Types
Lead/Public Agency

Location

Cities
Healdsburg
Counties
Sonoma
Cross Streets
Ida Clayton Rd., Calistoga CA
Zip
94515
Total Acres
656+/-1
Parcel #
120-090-023 & 120-040-011
State Highways
HWY128
Waterways
Yellow Jacket Creek, Mill Creek, Redwood Creek
Township
9N
Range
7W
Section
17,18
Base
MBM
Other Location Info
City/Nearest Community: Calistoga

Notice of Determination

Approving Agency
Sonoma County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A