Folsom Plan Specific Area Plan Project (Streambed Alteration Agreement No. 1600-2012-0198-R2 Amendment 2)

28 Documents in Project

Summary

SCH Number
2008092051
Lead Agency
City of Folsom
Document Title
Folsom Plan Specific Area Plan Project (Streambed Alteration Agreement No. 1600-2012-0198-R2 Amendment 2)
Document Type
NOD - Notice of Determination
Received
Posted
8/17/2018
Present Land Use
PLU: AG-80 (also AR-10, AG-20, SPA, RCA)
Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2012-0198-0198-R2, pursuant to section 1602 of the Fish and Game Code to the project applicant, Folsom South Area Group. The project is to allow the Folsom South area Group and its employees, agents, or contractors and their subcontractors to conduct the authorized activities associated with the Folsom Specific Plan Area (SPA). Amendment No. 2 includes additional offsite improvements including a detention basin, road improvements, trails and utility crossings. Additional impacts of approximately 0.154 acres will be mitigated consistent with the subject Master Agreement sub notification previously approved.

Contact Information

Name
Suzanne Gilmore
Agency Name
CDFW
Contact Types
Lead/Public Agency

Location

Cities
Folsom
Counties
Sacramento
Cross Streets
U.S. Highway 50, Prairie City Road, White Rock Road, Empire Ranch Rd.
Zip
95630
Total Acres
3,584
State Highways
US 50
Railways
RT, Union Pacific
Schools
Folsom HS, others
Waterways
Alder Creek, American River, Coyote Creek, Deer Creek

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.