Agreement 2008-0150-R4 - North Fork of Willow Creek Intake
7 Documents in Project
Summary
SCH Number
2008091066
Lead Agency
State Water Resources Control Board
Document Title
Agreement 2008-0150-R4 - North Fork of Willow Creek Intake
Document Type
NOD - Notice of Determination
Received
Posted
12/12/2011
Document Description
The Project consists of installation of a water intake for a municipal water supply. Approximately 2 cy of debris and sediment will be cleared from the bottom of the pool, and a wall screen and compressed air piping from the pump station located outside of the creek. All piping will be anchored to the rock face next to the intake pool. Existing access roads will be used, and no riparian vegetation will be removed. Disturbed areas will be restored and revegetated.
Contact Information
Name
Julie Means
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
Madera
Township
7S
Range
22E
Notice of Determination
Approving Agency
DFG
Approving Agency Role
Responsible Agency
Determinations
(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.