Plot Plan No. 25422

7 Documents in Project

Summary

SCH Number
2008061136
Lead Agency
Riverside County
Document Title
Plot Plan No. 25422
Document Type
NOD - Notice of Determination
Received
Posted
3/22/2016
Present Land Use
Undeveloped/Industrial Park/Light Industrial
Document Description
The plot plan proposes to develop two industrial buildings totaling 814,630 sf. Building 1 is intended as a logistics warehouse and will occupy 598,190 sf and building 3 will be designated for general or multi-tenant warehousing and will occupy 216,440 sf. The project will also include 581 parking spaces and two detention basins. The EIR studies the environmental impacts of the proposed project. This project was previously approved as plot plan 22925. A subsequent law suit and settlement agreement required the approvals to be vacated and reprocessed with the inclusion of a biological corridor. The project has changed the layout and the number of structures. Impacts are generally reduced by the new design. An EIR was previously done for the site, EIR510, which was also vacated. A new revised focused EIR has been drafted building on the previous EIR510.

Contact Information

Name
Matt Straite
Agency Name
Riverside County Planning Department
Contact Types
Lead/Public Agency

Location

Cities
Riverside
Counties
Riverside
Cross Streets
Alessandro Boulevard, Brown Street, Gem Lane
Zip
92518
Total Acres
54.53
Parcel #
297-080-007,008,009,010
State Highways
I-215
Railways
BNSF
Airports
March Air Reserve Base
Schools
Benjamin Franklin ES
Waterways
Drainage along northern and southern boundary
Township
3S
Range
4W
Section
16
Base
SBB&M
Other Location Info
March Air Reserve

Notice of Determination

Approving Agency
Riverside County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes