3280 Scott@ The Square Final Response Plan

13 Documents in Project

Summary

SCH Number
2008052065
Lead Agency
City of Santa Clara
Document Title
3280 Scott@ The Square Final Response Plan
Document Type
NOD - Notice of Determination
Received
Posted
4/10/2017
Document Description
Project consists of approval of a Final Response Plan by the DTSC for the 3280 Scott@ The Square Site prior to its redevelopment. DTSC is overseeing cleanup at the Site under agreements pursuant to the CA Land Reuse and Revitalization Act of 2004, CA Health and Safety Code Section 25395.60 et seq. ("CLRRA"), with 3200 Coronado Drive, LLC and 3130 Coronado Drive LLC. The purpose of the Response Plan is to reduce the potential risk to human health from the contaminants of concern, arsenic and lead in soil. Response activities to be conducted pursuant to the Response Plan include one or a combination of the following approaches: - Approach 1 - Relocating and consolidating impacted soil beneath a physical cap (building foundations) and/or - Approach 2 - Capping impacted soil in place beneath building foundations, other hardscape (parking or patio areas), or two feet of clean fill in landscaped area.

Contact Information

Name
Jayantha Randeni
Agency Name
DTSC
Contact Types
Lead/Public Agency

Location

Cities
Santa Clara
Counties
Santa Clara
Cross Streets
Bowers Avenue, Augustine Blvd., Scott Blvd.
Zip
95050
Parcel #
216-45-009, -011, -014, -019, -027, -028, -031, -032
State Highways
101, 237, 82
Railways
UPRR,SPRR
Airports
San Jose International
Schools
Mission College
Waterways
San Tomas Aquino & Calabazas Creek, Guadalupe River

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print