St John's Episcopal Church (ER08-0001) - Parking, Bridge, and New Sanctuary Expansion

4 Documents in Project

Summary

SCH Number
2008032031
Lead Agency
City of Oakland
Document Title
St John's Episcopal Church (ER08-0001) - Parking, Bridge, and New Sanctuary Expansion
Document Type
NOD - Notice of Determination
Received
Posted
3/24/2016
Present Land Use
R-30, One-family Residential Zone; Hillside Residential GP Designation
Document Description
Phase 1 consits of demolition of an existing single family welling, abandonment of a portion of the shared access road with 5940 Thornhill and 1675 Gouldin Road, construction of a new access bridge over Temescal Creek, reconfiguration of the site circulation and parking, and removal of 65 trees, 56 of which fall under the City of Oakland tree preservation ordinance. Phase 2 involves construction of a new sanctuary building between 5,000 and 5,500 square feet and related site improvements. The existing sanctuary would be converted into a community hall and fellowship space.

Contact Information

Name
Caesar Quitevis
Agency Name
City of Oakland, CEDA Planning & Zoning
Contact Types
Lead/Public Agency

Location

Cities
Oakland
Counties
Alameda
Cross Streets
Thornhill Drive and Gouldin Road
Zip
94611
Total Acres
3.13
Parcel #
048F-7390-004-09, 001-01, 003-03, 013-00, 001-018
State Highways
Hwy 13
Railways
N/A
Airports
N/A
Schools
Thornhill Elementary (5858 Thornhill Dr.)
Waterways
Temescal Creek

Notice of Determination

Approving Agency
City of Oakland Planning Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes