SAA 1600-2008-0047-R2
2 Documents in Project
Summary
SCH Number
2008012102
Lead Agency
Plumas County
Document Title
SAA 1600-2008-0047-R2
Document Type
NOD - Notice of Determination
Received
Posted
4/24/2008
Present Land Use
Zoning: R10, FP
General Plan: Moderate Opportunity Area, Rural
Document Description
The California Department of Fish and Game is executing Lake or Streambed Alteration Agreement number 1600-2008-0047-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, Feather River Coordinated Resource Management.
Silver Creek Rehabilitation Projector: The proposed treatments would install naturally occurring features and processes to capture and store some of the bedload material from upstream reaches, transport the remainder of material through the project reach, and significantly reduce erosion of stream banks. The project consists of installing one log jam and enhancing another existing log jam (80 cu yds of whole trees), installing 6 boulder vanes (120 cu yds of 3-6' boulders), installing boulder toe rap on one outcurve bank (50 cu yds of 3-6' boulders), raising 4-6 riffles (80 cu yds of 2' minus pit run), laying back 830 feet of bank 12 feet (184 cu yds material), and building floodplain bench using the opposing gravel bar (138 cu yds) and bank lay back material. The channel cross-sectional area will remain the same, but flow vectors will be directed away from banks using these treatments.
Contact Information
Name
Gary L. Hobgood
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
Plumas
Cross Streets
Silver Creek Road (County Road)
Parcel #
113-030-003
Waterways
Silver Creek and Spanish Creek
Township
24N
Range
8
Section
15
Base
MDB&M
Other Location Info
City/Nearest Community: Meadow Valley
Notice of Determination
Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes