Transfer of Parcels D-2, UC-1, and UC-2 of the Hunters Point Shipyard

11 Documents in Project

Summary

SCH Number
2007082168
Lead Agency
San Francisco Redevelopment Agency
Document Title
Transfer of Parcels D-2, UC-1, and UC-2 of the Hunters Point Shipyard
Document Type
NOD - Notice of Determination
Received
Posted
10/29/2015
Present Land Use
Various
Document Description
Acceptance by the Executive Director on Sep 9, 2015, of the US Navy's tender of Parcels UC-1, UC-2 and D-2 of the Hunters Point Shipyard, as authorized by the Commission on Community Investment and Infrastructure, by Resolution No. 54-2015, on Sep 1, 2015, in furtherance of the implementation of the Candlestick Park - Hunters Point Shipyard Phase II Project. The Redevelopment Agency approved the Candlestick Park - Hunters Point Shipyard Phase II Project on August 3, 2010. This notice is with respect to the undertaking described above and a determination made under Section 15180, including Sections 15162, 15163, and 15168.

Contact Information

Name
Jose Campos
Agency Name
Successor Agency to SF Redevelopment
Contact Types
Lead/Public Agency

Location

Cities
San Francisco
Counties
San Francisco
Zip
94124
Total Acres
702
Parcel #
4591A002, 4591A076, 4591A077, etc.
State Highways
US 101 and US 280
Railways
CalTrain,San Francisco Municipal
Schools
Bret Harte ES, Malcom X Academy ES, Washington Caroe ES, Mult.
Waterways
SF Bay and Yosemite Slough

Notice of Determination

Approving Agency
Successor Agency to SF Redevelopment agency
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print