Enchanted Heights Wastewater Collection System

6 Documents in Project

Summary

SCH Number
2007051071
Lead Agency
Eastern Municipal Water District
Document Title
Enchanted Heights Wastewater Collection System
Document Type
NOD - Notice of Determination
Received
Posted
7/30/2007
Present Land Use
Rural Residential
Document Description
Eastern Municipal Water District proposes to construct a gravity wastewater collection system to serve the Enchanted Heights service area. The gravity system will consist of laterals to residences, mainline piping and manholes, and a lift station. The laterals to be constructed as a part of this project will be for only that portion of the lateral that is not on private property and will connect with a wye to the top of the mainline. The mainline will consist of an 8-inch diameter PVC pipeline that will be placed on the opposite sides of the streets from the existing water main and will be laid on a downward slope so that the wastewater flows by gravity. Manholes will be placed at regular intervals to allow cleaning and maintenance access. The lift station will consist of a wet well to collect the wastewater and pumps to lift the wastewater to a point so that is can be discharged back into another gravity sewer for transport to the treatment facilities.

Contact Information

Name
Karen Hackett
Agency Name
Eastern Municipal Water District
Contact Types
Lead/Public Agency

Location

Counties
Riverside
Regions
Unincorporated
Cross Streets
Area bounded by Metz Road, Bond Drive, San Jacinto Avenue, and Lukens Lane
Zip
92570, 571
State Highways
74
Schools
Perris
Township
4S
Range
4W
Section
25
Base
SBB&M

Notice of Determination

Approving Agency
Eastern Municipal Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project