Turtle Back Hill Trail Accessibility Improvements Project - China Camp State Park

2 Documents in Project

Summary

SCH Number
2007032060
Lead Agency
California Department of Parks and Recreation
Document Title
Turtle Back Hill Trail Accessibility Improvements Project - China Camp State Park
Document Type
NOD - Notice of Determination
Received
Posted
5/1/2007
Present Land Use
Open Space (County of Marin General Plan Update)
Document Description
Reroute of approximately 3,220 linear feet (lf) of trail to reduce linear grades, convert approximately 230 lf of existing dirt road to trail by reducing width, construct approximately 110 lf of four-foot-wide eleveated boardwalk, and armor the trail tread. Total length of ADA-compliant trail wil be approximately 3,560 lf upon completion. Approximately 1,000 lf of existing road (currently used as a trail) and approximately 1,600 lf of existing trail will be obliterated, decompacted, and revegetated with native vegetation.

Contact Information

Name
Gail Sevrens
Agency Name
California Department of Parks and Recreation
Contact Types
Lead/Public Agency

Location

Cities
San Rafael
Counties
Marin
Cross Streets
North San Pedro Road and Sunny Oaks Drive
Zip
94901
Total Acres
1.3
Parcel #
186-010-12 and 186-010-17
Railways
Northwestern Pacific RR
Waterways
San Pablo Bay/San Francisco Bay, Gallinas Creek, unnamed stream reaches and ponds
Township
Land
Other Information
Township: Land Grant

Notice of Determination

Approving Agency
Department of Parks and Recreation
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print