Ecology Control Industries, Fontana, Closure Plan

2 Documents in Project

Summary

SCH Number
2006121038
Lead Agency
Department of Toxic Substances Control
Document Title
Ecology Control Industries, Fontana, Closure Plan
Document Type
NOD - Notice of Determination
Received
Posted
4/24/2007
Present Land Use
Industrial
Document Description
DTSC is approving a closure plan for the Storage Tank Recycler with Environmental Protection Agency (EPA) identification (ID) Number CAD 982484933 for Ecology Control Industries, hereafter ECI Fontana. The Closure Plan (CP) includes procedures to be used to decontaminate and close the ECI Fontana facility. This CP was prepared and submitted following guidelines contained in California Code of Regulations, title 22, Section 66264.112. This Initial Study examines the potential impacts associated with closure activities. The Closure Plan and Soil Sampling Plan to Evaluate Site Conditions for Closure are incorporated by reference.

Contact Information

Name
Ryan Batty
Agency Name
Department of Toxic Substances Control
Contact Types
Lead/Public Agency

Location

Cities
Fontana
Counties
San Bernardino
Cross Streets
Slover Avenue and Mulberry Avenue
Zip
92337
Total Acres
1.4
Parcel #
0236-011-08-P001; 235-01-1009-P001
State Highways
10
Railways
SPRR (north)
Schools
Henry J. Kaiser, Chaparral ES, Shadow Hills ES, Southridge MS, L
Township
1S
Range
6W
Section
21,27,
Base
Fontana
Other Information
Section: 28 Schools: Live Oak ES, Canyon Crest ES, Oak Park ES.

Notice of Determination

Approving Agency
DTSC
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No