Hospitality Lane Commercial Mixed Use Project - Tentative Parcel Map No. 17772 (SUB No. 06-02), Conditional Use Permit No. 06-26, & Conditional Use Permit No. 0
4 Documents in Project
Summary
SCH Number
2006121033
Lead Agency
City of San Bernardino
Document Title
Hospitality Lane Commercial Mixed Use Project - Tentative Parcel Map No. 17772 (SUB No. 06-02), Conditional Use Permit No. 06-26, & Conditional Use Permit No. 0
Document Type
NOD - Notice of Determination
Received
Posted
7/20/2007
Present Land Use
The project site is presently vacant land.
GP: Community Commercial
Z: Commercial Regional-3 (CR-3)
Document Description
A request to subdivide approximately 7.2 acres into four parcels ranging in size from 1.72 to 2.42 acres, with a request to construct two multi-tenant retail centers (one 7,800 square feet and one 7,000 square feet) and two hotels (Homewood Suites, a 4-story extended stay, 103-unit facility and Hampton Inn & Suites, a 4-story traditional stay, 110-unit facility).
Contact Information
Name
John Oquendo
Agency Name
City of San Bernardino
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Bernardino
Counties
San Bernardino
Cross Streets
Hospitality Lane and Tippecanoe Avenue
Zip
92418
Total Acres
7.2
Parcel #
0281-361-06-0-000
State Highways
I-10
Railways
BNSF and UPRR
Airports
San Bernardino International
Schools
Burbank ES, Loma Linda Academy HS, Loma Linda University
Waterways
Gage Canal
Township
1S
Range
4W
Section
23
Base
SBBM
Notice of Determination
Approving Agency
City of San Bernardino Planning Commission
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.