Funding Mechanism for Comprehensive Sacramento Area Flood Protection and Natomas Cross Canal South Levee Phase I Improvements Project
11 Documents in Project
Summary
SCH Number
2006072098
Lead Agency
Sacramento Area Flood Control Agency
Document Title
Funding Mechanism for Comprehensive Sacramento Area Flood Protection and Natomas Cross Canal South Levee Phase I Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
4/23/2007
Present Land Use
Various, including flood control works, agriculture, and public right-of-way
Document Description
The California Dept. of Fish and Game is executing Lake or Streambed Alteration Agreement number 1600-2007-0085-R2, pursuant to Section 1602 of the Fish and Game Code to the project applicant, Sacramento Flood Agency.
Natomas Cross Canal South Levee Phase 1 Improvement, The proposed project involves the construction of a "cutoff wall" through the levee crown in the south levee of the Natomas Cross Canal.
Contact Information
Name
John Bassett
Agency Name
The Reclamation Board
Contact Types
Lead/Public Agency
Phone
Location
Cross Streets
Various
State Highways
5, 99, 80
Airports
Sacramento International
Waterways
Sacramento&American Rivers,Natomas Cross Canal,Morrison Creek&tributaries,Natomas East Main ....
Other Location Info
City/Community: Natomas
Other Information
waterways: Natomas East Main Drainage Canal & tributaries
Notice of Determination
Approving Agency
Dept. of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes