Live Oak Bridge and Toyon Water System Improvements, Anderson Lake County Park

3 Documents in Project

Summary

SCH Number
2006072003
Lead Agency
Santa Clara County
Document Title
Live Oak Bridge and Toyon Water System Improvements, Anderson Lake County Park
Document Type
NOD - Notice of Determination
Received
Posted
8/31/2006
Present Land Use
Existing Regional Parklands
Document Description
Construction of a bridge and water system improvements in the Live Oak and Toyon picnic areas in Anderson Lake County Park. Live Oak Bridge component - construct a bridge across Coyote Creek to access the existing Live Oak picnic area. Access formerly via an earthen fill crossing over two culverts. Due to controlled floodwater release from Anderson Reservoir by Santa Clara Valley Water District, this crossing washed out. Water line improvements consist of replacement of an existing degraded 2" water line with a new 4" and 3" line from an existing water main service to an existing restroom facility. Lateral water lines will also be installed to replace degraded water lines for drinking water, hose bibs, etc.

Contact Information

Name
Antoinette Romeo
Agency Name
Santa Clara County Parks and Recreation Department
Contact Types
Lead/Public Agency

Location

Cities
Morgan Hill
Counties
Santa Clara
Cross Streets
19245 Malaguera Avenue, Morgan Hill
Zip
95037
Total Acres
14
Parcel #
728-34-020, 021, 019; 729-48-001
Waterways
Coyote Creek
Township
9S
Range
3E
Section
10
Base
MD

Notice of Determination

Approving Agency
Santa Clara County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A