MCWD Tanks Improvements Project

3 Documents in Project

Summary

SCH Number
2006061042
Lead Agency
Marina Coast Water District
Document Title
MCWD Tanks Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
4/26/2007
Present Land Use
Public facilities
Document Description
The proposed project will consist of demolition of the existing D Zone Reservoir, E Zone Tank and pump station, and construction of a new D Zone Reservoir, a closed system hydropneumatic pump station to serve E Zone, and offsite storm drain and potable water pipeline for both the D and E Zones. In addition, the proposed improvements include demolition of the Airport Tank and Bayer Tank. The proposed action is part of MCWD's Capital Improvements Plan (CIP) identified within the 2004 Ord Community Water Distribution System Master Plan. Improvements to the system's storage facilities are necessary to meet the projected future demands, as well as comply with current State Department - Department of Health Services (DHS) regulations for potable water distribution systems.

Contact Information

Name
Ken Demmons
Agency Name
Marina Coast Water District
Contact Types
Lead/Public Agency

Location

Cities
Marina, Seaside
Counties
Monterey
Cross Streets
Parker Flats cutoff/Eucalyptus Road, Bayer Drive, and Imjin and Neeson Road
Zip
93955
State Highways
Hwy. 1
Schools
CSUMB
Other Location Info
Former Fort Ord

Notice of Determination

Approving Agency
Marin Coast Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes