Crafton Hills College Master Plan

8 Documents in Project

Summary

SCH Number
2006011080
Lead Agency
San Bernardino Community College District
Document Title
Crafton Hills College Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
7/16/2013
Present Land Use
College/IN-Institutional/IN-Institutional
Document Description
The CHC Master Plan Update (March 2013) describes the future development of the CHC in two horizons, keeping with the planning strategies and framework of the 2005 Master Plan. Horizon 1 includes the Measure 'M' priority projects as identified by the Master Plan Steering Committee. Horizon 2 is the potential full build-out of the campus in the future. The SEIR only analyzes Horizon 1, because not enough detail is known about future projects. Separate CEQA documentation will be prepared for Horizon 2 as projects become defined and funding sources become available.

Contact Information

Name
Tim Oliver
Agency Name
San Bernardino Community College District
Contact Types
Lead/Public Agency

Location

Cities
Highland, Redlands, Yucaipa
Counties
San Bernardino
Cross Streets
San Canyon Road, Campus Drive, Yucaipa Boulevard
Zip
92399
Total Acres
513
Parcel #
0299-311-07, -08, 0299-321-45, -58, -59, and -66
State Highways
I-10
Schools
Yucaipa High School,
Waterways
Dunlap Channel, Wilson Creek, Gateway Wash
Township
1S
Range
2W
Section
32, 33
Base
SBB&M

Notice of Determination

Approving Agency
San Bernardino Community College District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.