Chevron Revised Energy and Hydrogen Renewal Project
4 Documents in Project
Summary
SCH Number
2005072117
Lead Agency
City of Richmond
Document Title
Chevron Revised Energy and Hydrogen Renewal Project
Document Type
NOP - Notice of Preparation
Received
Present Land Use
M-3 (Heavy Industrial)
Document Description
The Chevron Richmond Refinery (the Refinery) is located at 841 Chevron Way in the City of Richmond. The proposed Chevron Energy and Hydrogen Renewal Project involves four main components: Hydrogen Plant Replacement, Reformer Replacement, Power Plant Replacement, and Hydrogen Purity Improvements. The Renewal Project would replace and alter facilities within existing manufacturing areas of the Refinery. In addition, a hydrogen pipeline, external to the Refinery, will be part of the project.
Other smaller projects to update plant equipment are also under consideration. These other projects could involve the addition and/or replacement of approximately six storage tanks, additional truck traffic through the Marketing terminal, and a post-construction cumulative impacts analysis - as ordered by the court - of an already-completed project to build two new LPG spheres.
Chevron proposes the Renewal Project to increase energy efficiency, to improve equipment and process reliability, and to reduce air emissions. The Renewal Project would improve the Refinery's ability to process crude oil and other feed stocks from around the world and to direct more of current gasoline production capacity to the California market.
The proposed project would require a Conditional Use Permit from the City of Richmond and Design Review. The project will also require a Bay Area Air Quality Management District (BAAQMD) Authority to Construct and Permit to Operate (ATC/PTO).
Contact Information
Name
Morty Prisament
Agency Name
City of Richmond
Contact Types
Lead/Public Agency
Phone
Location
Cities
Richmond
Counties
Contra Costa
Cross Streets
Castro Street / Richmond Parkway and San Pablo Bay
Zip
94804
Parcel #
561-100-002
State Highways
580
Railways
Santa Fe Railyards
Waterways
San Pablo Bay
Other Location Info
841 Chevron Way
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
Air Resources Board, Major Industrial Projects, California Coastal Commission (CCC), California Department of Fish and Wildlife, Bay Delta Region 3 (CDFW), California Department of Parks and Recreation, California Energy Commission, California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, San Francisco Bay Region 2 (RWQCB), California State Lands Commission (SLC), Department of Toxic Substances Control, Office of Emergency Services, California, Resources Agency, San Francisco Bay Conservation and Development Commission (BCDC), California Native American Heritage Commission (NAHC), California Department of Transportation, District 4 (DOT)
State Reviewing Agency Comments
San Francisco Bay Conservation and Development Commission (BCDC), California Native American Heritage Commission (NAHC), California Department of Transportation, District 4 (DOT)
Development Types
Industrial , Other (Refinery)
Local Actions
Use Permit
Project Issues
Aesthetics, Air Quality, Biological Resources, Cultural Resources, Cumulative Effects, Drainage/Absorption, Geology/Soils, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Noise, Population/Housing, Public Services, Transportation
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.