Bear Mountain Road Realignment
2 Documents in Project
Summary
SCH Number
2005072061
Lead Agency
Shasta County
Document Title
Bear Mountain Road Realignment
Document Type
NOD - Notice of Determination
Received
Posted
6/30/2006
Present Land Use
Rural Residential and Recreational Uses.
Z: Rural Residential
GP: Rural Residential
Document Description
The project involves the realignment of approximately 2,000 feet of Bear Mountain Road to remove substandard horizontal and vertical curves, and improve sight distance. The roadway will be widened from an existing roadway width averaging 23 feet with little or no shoulder to 32 feet of paved roadway with four-foot graded shoulders on each side. Roadway cuts are anticipated to be up to 20 feet, with fills of up to seven feet. An existing 290-foot radius curve will be replaced with a 660-foot radius curve allowing an 45 MPH design speed; the existing roadway wil be demolished and removed. The project will also involve the relocation of three utility poles, an underground telephone line, guardrails, mailboxes, fences, and signs; and the alteration of drainage ditches, culverts, driveways, and the intersection of Bear Mountain Road and Jennifer Drive. The project will require approximately two acres of new right-of-way acquisition from nine separate parcels.
Contact Information
Name
Bill Ramsdell
Agency Name
Shasta County Department of Public Works
Contact Types
Lead/Public Agency
Phone
Location
Cities
Redding
Counties
Shasta
Cross Streets
Bear Mountain Road / Dry Creek Road
Zip
96003
Total Acres
~ 2
Waterways
Stillway Creek / Lake Shasta
Township
33N
Range
4W
Section
28
Base
MDBM
Notice of Determination
Approving Agency
Shasta County Board of Supervisors
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.