Waterline Intertie Project and Agreement with Nipomo Community Services District on the Sale and Delivery of Supplemental Water
12 Documents in Project
Summary
SCH Number
2005071114
Lead Agency
Nipomo Community Services District
Document Title
Waterline Intertie Project and Agreement with Nipomo Community Services District on the Sale and Delivery of Supplemental Water
Document Type
NOD - Notice of Determination
Received
Posted
12/19/2011
Document Description
Construction of a waterline from the City of Santa Maria to the Nipomo Community Services District water distribution and the potential importation of a maximum of 6,200 acre ft. of water per year to the District. The pipeline will be constructed beneath the Santa Maria River by horizontal directional drilling. A pump station(s) and water storage facilities will be constructed, water transmission facilities will be upgraded or replaced and District water supply wells will be converted from chlorination to chloramination.
Contact Information
Name
Mark Hutchinson
Agency Name
County of San Luis Obispo
Contact Types
Lead/Public Agency
Phone
Location
Cities
Nipomo
Counties
San Luis Obispo
Cross Streets
Orchard and Joshua
Zip
93444
State Highways
101
Railways
Southern Pacific
Airports
Santa Maria
Schools
Dana, Nipomo Elem
Waterways
Santa Maria River
Township
12N
Range
35W
Notice of Determination
Approving Agency
County of San Luis Obispo
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
N/A