Conveyance of 2020 Water Transfers from Cordua Irrigation District to Dudley Ridge Water District, Alameda County Water District, County of Kings, and Kern...

28 Documents in Project

Summary

SCH Number
2005062111
Lead Agency
Yuba County Water Agency
Document Title
Conveyance of 2020 Water Transfers from Cordua Irrigation District to Dudley Ridge Water District, Alameda County Water District, County of Kings, and Kern...
Document Type
NOD - Notice of Determination
Received
Posted
9/29/2020
Document Description
Cordua is conducting a one-year 2020 groundwater substitution transfer. Cordua will pump up to an additional 9,198 acre-feet of groundwater from July through September 2020 to substitute for reduced deliveries of surface water under its pre-1914 water right. With deduction of June fisheries release and a 13 percent stream flow depletion, up to 7,142 acre-feet of the forgone surface water will enter the Sacramento-San Joaquin Delta (Delta). After Delta carriage water, DWR will export the water through State Water Project Banks Pumping Plant and deliver to DRWD, ACWD, KC and KCWA during July through September 2020.

Contact Information

Name
Brian Heiland
Agency Name
Department of Water Resources
Contact Types
Lead/Public Agency

Location

Counties
Alameda, Kern, Kings, Yuba
Other Location Info
Cordua Irrigation District (Cordua) is located in Yuba County. The water will be delivered to the service areas of Dudley Ridge Water District (DRWD), Alameda County Water District (ACWD), County of Kings (KC), and Kern County Water Agency (KCWA). The Project will use existing State Water Project facilities.

Notice of Determination

Approving Agency
DWR
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes