Grossmont Trolley Court Apartments Tentative Tract Map TTM 04-02, Site Development Plan DAB 04-05, Special Permit SP 04-10 and Design Review DRB 04-05
3 Documents in Project
Summary
SCH Number
2005051153
Lead Agency
City of La Mesa
Document Title
Grossmont Trolley Court Apartments Tentative Tract Map TTM 04-02, Site Development Plan DAB 04-05, Special Permit SP 04-10 and Design Review DRB 04-05
Document Type
NOD - Notice of Determination
Received
Posted
6/18/2009
Document Description
The project consists of a 527 unit, multi family residential development with supporting commercial retail uses, recreational facilities and 2 above ground parking garages on a 7.5 acre site. The project also includes improvements to the existing Grossmont Trolley Station, off-site utility improvements and a street vacation. The site is designated Public Uses/Transportation Uses: Trolley Station in the La Mesa General Plan and is zoned General Commercial/Grossmont Specific Plan Overlay Zone/Urban Design Overlay Zone.
Contact Information
Name
Agency Name
California Transportation Commission
Contact Types
Lead/Public Agency
Phone
Location
Cities
La Mesa
Counties
San Diego
Cross Streets
Fletcher Parkway / Grossmont Center Drive
Zip
91942
Total Acres
7.5
Parcel #
490-270-23, 25; 490-200-39, 40
State Highways
125
Railways
MTS Orange Line
Schools
Parkway MS
Waterways
Alvarado Creek, Lake Murray
Township
16S
Range
1W
Base
La Mesa
Other Information
Base: Quadrangle
Notice of Determination
Approving Agency
CA Transportation Commission
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.