Airport Boulevard Realignment
4 Documents in Project
Summary
SCH Number
2005051146
Lead Agency
California Department of Transportation, District 5
Document Title
Airport Boulevard Realignment
Document Type
NOD - Notice of Determination
Received
Posted
4/23/2009
Document Description
The CDFG is executing a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game code to the Project applicant. Caltrans proposes to re-align the existing channel which currently flows parallel to De La Torre Street. The channel needs to be moved to the east a variable distance ranging from 20 to 80 ft. The existing channel has ~10 ft bottom with 1.5:1 side slopes. The new channel would have a 12 ft bottom and also 1.5:1 side slopes. When the channel is re-aligned, the existing culvert under Airport Blvd will be replaced with a new 12 ft x 12ft concrete box culvert. Rock slope protection will be placed along the banks at the outlet of the culvert to protect the channel from potential erosion due to the sharp turn. This particular location always has irrigation run-off water present year-round. A diversion plan submitted as part of the Notification.
Contact Information
Name
Laura Peterson-Diaz
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Salinas
Counties
Monterey
Cross Streets
Airport / Deletorre
Zip
93908
Total Acres
~ 10
State Highways
101
Airports
Salinas
Notice of Determination
Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.