Otay Mesa Power Purchase Agreement Transmission Project Proposed by San Diego Gas and Electric (Application No. A.04-03-008)

4 Documents in Project

Summary

SCH Number
2004071138
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Otay Mesa Power Purchase Agreement Transmission Project Proposed by San Diego Gas and Electric (Application No. A.04-03-008)
Document Type
NOD - Notice of Determination
Received
Posted
8/8/2005
Present Land Use
Local Business / Commercial / Residential / Military
Document Description
The proposed project includes a new 230 kV electric transmission circuit that will connect Calpine's Otay Mesa Generation Project (OMGP), currently under construction near SDG&E's existing Miguel Substation, with SDG&E's existing Sycamore Canyon Substation, and a second 230 kV electric transmission circuit that will connect the OMGP to SDG&E's existing Old Town Substation. Additional project components will include a new transition station and modifications to the existing Sycamore Canyon, Miguel and Old Town Substations.

Contact Information

Name
Billie Blanchard
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
Chula Vista, National City, San Diego
Counties
San Diego
Cross Streets
Multiple transmission line project
Zip
multiple
Total Acres
N/A
State Highways
I-5, I-805, SR-54, SR-67, I-8
Airports
S.D. Lindbergh Field, US MCAS
Schools
Chula Vista ES, Sweetwater Union HS, San Diego USD
Waterways
N/A

Notice of Determination

Approving Agency
California Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes