Summary
SCH Number
2004041081
Lead Agency
San Diego County Water Authority
Document Title
Carlsbad Desalination Plant’s Phase II–Discharge Pond Blocks & Relocate/Replace Gangway/Dock Project
Document Type
NOD - Notice of Determination
Received
Posted
3/6/2020
Present Land Use
Encina Power Station and Carlsbad Desalination Plant
Document Description
The San Diego Regional Water Quality Control Board issued a Clean Water Act Section 401 water quality certification (Cert. #R9-2020-0090) to the applicant to place 57 concrete blocks within the discharge pond, a tidal pond adjacent to the Pacific Ocean, and relocate and replace the floating dock and gangway from the south side of the pond to the west side. The pond floor will be scraped and leveled to ensure secure placement on the pond floor. No eelgrass habitat occurs within the pond. To protect water quality, the installation will be performed when the plant is not operating, and a temporary silt curtain will be deployed to contain turbidity.
Contact Information
Name
Lisa Honma
Agency Name
Regional Water Quality Control Board, Region 9 San Diego
Contact Types
Lead/Public Agency
Phone
Name
Agency Name
Poseidon Resources (Channelside) LP
Contact Types
Project Applicant
Location
Coordinates
Cities
Carlsbad
Counties
San Diego
Regions
Southern California
Cross Streets
3590 Carlsbad Blvd, aka S. Coast Highway 101, Carlsbad, CA 92008
Zip
92008
Parcel #
210-010-43
State Highways
S. Coast Highway 101
Waterways
Discharge pond connected to Pacific Ocean, adjacent to Agua Hedionda Lagoon
Notice of Determination
Approving Agency
Regional Water Quality Control Board, Region 9 San Diego
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes