Public Safety Facilities Master Plan

4 Documents in Project

Summary

SCH Number
2004031142
Lead Agency
City of Los Angeles
Document Title
Public Safety Facilities Master Plan
Document Type
NOD - Notice of Determination
Received
Posted
7/22/2005
Present Land Use
Commercial, public facilities, and industrial
Document Description
The project includes the construction of public safety facilities in downtown Los Angeles which were included under the Proposition Q (Public Safety Facilities) and F (Fire Facilities) bond measures approved by voters. A new 179,000 square-foot Metro Jail would be constructed south of Temple and Los Angeles Streets to replace the existing central jail at Parker Center at 150 N. Los Angeles Street. A new 82,000 square-foot Emergency Operations Center-Police Operations Center-Fire Dispatch Center (EOC-POC-FDC) would be constructed adjacent to the west of the new EOC-POC-FDC to replace the existing Fire Station No. 4 at 800 N. Main Street. The new fire station would contain a 147-space surface parking lot to the south with a small pocket of open space farther south on 1st Street. Related improvements such as street dedications and vacations would be provided for the facilities identified above. Construction of the project would start in late 2005/early 2006 and end by late 2007. The project would cause significant environmental impacts related to aesthetics, air quality, cultural resources, hazardous materials, noise and vibration, and traffic and parking. Most of these impacts would occur during construction. With the implementation of feasible mitigation measures, significant and unavoidable adverse impacts to aesthetics, air quality, historical resources, noise and vibration, and traffic would remain.

Contact Information

Name
Lisa M. Ochsner
Agency Name
City of Los Angeles
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles, Los Angeles, City of
Counties
Los Angeles
Cross Streets
Los Angeles Street, Temple Street, Vignes Street and First Street
Zip
90012
Total Acres
20
State Highways
2,110 & 60
Railways
Metrolink, Amtrak, MTA
Schools
LAUSD
Waterways
Los Angeles River
Township
1S
Range
13W
Section
28,29
Base
SBBM

Notice of Determination

Approving Agency
City Council
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA