Silva Valley Parkway Water Main and Sewer Force Main Project
Summary
SCH Number
2003089013
Lead Agency
El Dorado Irrigation District
Document Title
Silva Valley Parkway Water Main and Sewer Force Main Project
Document Type
NOD - Notice of Determination
Received
Posted
8/5/2003
Document Description
The proposed project would involve the construction of approximately 11,000 lineal feet of 42-inch water main and approximately 6,500 lineal feet of 16-inch sewer force main. The project also includes upgrading the existing New York Creek and Timberline Lift Stations with replacement of existing pumps with new larger pumps.
Contact Information
Name
W. Chris Word
Agency Name
El Dorado Irrigation District
Contact Types
Lead/Public Agency
Phone
Location
Counties
El Dorado
Other Location Info
El Dorado Hills
Notice of Determination
Approving Agency
El Dorado Irrigation District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.