AC Transit East Bay Bus Rapid Transit Project in Alameda County

11 Documents in Project

Summary

SCH Number
2003052070
Lead Agency
Alameda Contra Costa Transit District (AC Transit)
Document Title
AC Transit East Bay Bus Rapid Transit Project in Alameda County
Document Type
NOD - Notice of Determination
Received
Posted
2/3/2016
Present Land Use
Street right-of-way / Commercial Property (very limited potential encroachments due to expanded public easements)
Document Description
AC Transit Board approved project on April 25,2012. As stated in original NOD filed April 2012, project will provide high level BRT service and related infrastructure along a 14.38-mile corridor connecting Berkeley-Oakland-San Leandro in Alameda County, subsequently modified to 9.5 miles from Downtown Oakland to the San Leandro BART Station. A 2014 amendment to NOD reflected addition of 2 BRT stations to project, relocation of several stations, and other design refinements. This NOD amendment reflects refinements since 2014, including additional minor stations relocations, a BRT bus layover and operator rest facility in central Oakland, and other minor modifications.

Contact Information

Name
David Wilkins
Agency Name
Alameda-Contra Costa Transit Dist
Contact Types
Lead/Public Agency

Location

Cities
Oakland, San Leandro
Counties
Alameda
Cross Streets
University Avenue, Broadway, Hesperian Boulevard
Zip
Multiple
State Highways
I-880, I-980, SR 24
Railways
UPRR
Waterways
Lake Merritt Channel, San Leandro Creek, Arroyo Viejo Creek, Estudillo Canal

Notice of Determination

Approving Agency
Alameda-Contra Costa Transit District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes