Addendum No. 1 to the Riverside Corona Feeder Project Supplemental EIR/EIS for the Realignment of Reach G, Realignment of a Portion of Reach F, and the Change i
10 Documents in Project
Summary
SCH Number
2003031121
Lead Agency
Western Municipal Water District
Document Title
Addendum No. 1 to the Riverside Corona Feeder Project Supplemental EIR/EIS for the Realignment of Reach G, Realignment of a Portion of Reach F, and the Change i
Document Type
NOD - Notice of Determination
Received
Posted
1/12/2016
Present Land Use
Various
Document Description
The project as evaluated in the 2012 SEIR/EIS consisted of approximately 30 miles of major feeder pipeline and related facilities located along an alignment generally running along the 91/215 freeway, from the City of San Bernardino on the northeast to the City of Corona on the Southwest. The facilities evaluated in Addendum No. 1 consist of realignment of Reach G, alignment of a portion of Reach F, and a change in the type and number of pumps to be installed in the Sterling Pump Station. No change to Reach E is proposed as part of the Modified Facilities.
The proposed realignment commences at the Arlington Desalter facility connecting through the site to the Sterling Pump Station for approximately 800 ft and then continues southwest across Sterling Ave through a private parcel to the Riverside County Flood Control and Water Conservation District's Arlington Channel for approximately 275 ft, then northeast approximately 2,825 ft along the north side of the Burlington Northern and Santa Fe rail lines within the right of way of RCFCWCD's Arizona Channel. At the Arizona Channel, jack and bore construction will be used to bore under the BNSF rail line and the channels. The pipeline will traverse approximately 1,900 ft southeast within the Arizona Channel ROW to RCFCWCD's Line C-1 ROW. The pipeline will continue in the Line C-1 ROW approximately 975 ft southeast to a point approximately 1,500 north of the intersection of La Sierra Ave/Indiana Ave. The pipeline will then continue in the original Reach F alignment to the intersection of La Sierra Ave/Cleveland Ave then continue south in La Sierra Ave to El Sobrante Ave following the La Sierra Pipeline alignment evaluated in the SEIR/EIS.
Contact Information
Name
Jimmy Chen
Agency Name
Western Municipal Water District
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Colton, Colton, Corona, Grand Terrace, Highland, Riverside, ..., Corona, Grand Terrace, Highland, Riverside
Counties
Riverside, San Bernardino
Cross Streets
Various
Zip
Various
Parcel #
Multiple
State Highways
I-15, I-10, SR-60, SR-91
Railways
BNSF, Southern Pacific
Airports
Riverside, Flabob
Waterways
Santa Ana River, Gage Canal
Township
2S
Range
6W
Base
SBB&M
Other Information
Cont. Airports: San Bernardino Int'l
Notice of Determination
Approving Agency
Western Municipal Water District
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.