Fiddyment Farms F55 (Streambed Alteration Agreement No. 1600-2020-0066-R2)

30 Documents in Project

Summary

SCH Number
2002082057
Lead Agency
City of Roseville
Document Title
Fiddyment Farms F55 (Streambed Alteration Agreement No. 1600-2020-0066-R2)
Document Type
NOD - Notice of Determination
Received
Posted
7/9/2020
Document Description
The project is part of a proposed 25-acre residential development which is proposed as part of the West Roseville Specific Plan. The proposed project includes the following four activities: 1. SD Outfall A: This activity consists of the creation of a bio-retention water quality basin, which will provide pre-treatment of stormwater runoff prior to its discharge into an existing topographic swale that will then flow to the creek, and the installation of a stormwater outfall. The basin will be excavated with a backhoe and backfilled with drain rock and pea gravel before being topped with a bio-retention soil mix with upland mix. Low flow stormwater will discharge through a low flow discharge point into the bio-retention basin prior to its discharge into the intermittent drainage. During high flow periods,such as major storm events, most of the flows will bypass the basin and discharge through a 30”stormwater outfall into a water quality swale before entering the existing topographic swale that flows off-site. 2. SD Outfall B: This activity consists of the creation of a bio-retention water quality basin, which will provide pre-treatment of stormwater runoff prior to its discharge into Coyote Creek, and the installation of a stormwater outfall. The basin will be excavated with a backhoe and backfilled with drain rock and pea gravel before being topped with a bio-retention soil mix with upland mix. Low flow stormwater will discharge through a low flow discharge point into the bio-retention basin prior to its discharge into Coyote Creek. During high flow periods, such as major storm events, most of the flows will bypass the basin and discharge through a 42” stormwater outfall into a water quality swale before entering Coyote Creek. 3. SD Outfall C: This activity consists of the creation of a bioretention basin and a water quality swale, which will provide pre-treatment of stormwater runoff prior to its discharge into Coyote Creek. The basin will be excavated with a backhoe and backfilled with drain rock and pea gravel before being 4. Mass Grading: This activity consists of mass grading of the project area to allow for residential development and associated infrastructure. No in-stream work will be required. Construction activity will occur while the existing drainage is dry

Contact Information

Name
Gabriele Quillman
Agency Name
California Department of Fish and Wildlife
Contact Types
Lead/Public Agency

Name
Agency Name
Jeff Jones, West Roseville, LLC
Contact Types
Project Applicant

Location

Counties
Placer
Regions
Northern California
Cross Streets
south of Blue Oaks Boulevard, west of Fiddyment Road, and east of Westpark Drive
Parcel #
492- 012-004 and 017-101-034
Waterways
coyote creek
Township
11N
Range
05E
Section
23 24

Notice of Determination

Approving Agency
California Department of Fish and Wildlife
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes