Hornblower Charter and Excursion Services

2 Documents in Project

Summary

SCH Number
2002042140
Lead Agency
City of South Lake Tahoe
Document Title
Hornblower Charter and Excursion Services
Document Type
NOD - Notice of Determination
Received
Posted
6/24/2002
Present Land Use
Stateline/ Ski Run Community Plan, Basin E District
Document Description
Amend the City of South Lake Tahoe's 1985 Special Use Permit for the Tahoe Queen to modify or delete obsolete conditions and to add new permit conditions and vessels to which the permit is applicable. In addition to the Tahoe Queen, this revised permit includes use of the Tahoe Paradise, Tahoe Princess, and the Meteor. Hornblower is authorized to substitute these vessels for any regularly scheduled Tahoe Queen excursion boat tour. Charter services would be added to the offering of regularly scheduled tours. However, passenger capacity utilizing both the charter and tour boat operations remains limited to a total of 1,950 during any 24-hour day. All four boats may be used in the charter capacity. Loading and unloading of charter or excursion passengers within the City will be authorized at the Ski Run Marina only. All other proposed docking facilities for the charter activities are outside of the City limits and have been permitted by the Tahoe Regional Planning agency.

Contact Information

Name
Lisa O'Daly
Agency Name
City of South Lake Tahoe
Contact Types
Lead/Public Agency

Location

Cities
South Lake Tahoe
Counties
El Dorado
Cross Streets
Ski Run Blvd & Hwy 50
Parcel #
029-690-06
State Highways
50
Waterways
Lake Tahoe
Township
13N
Range
18E
Section
33
Base
MDBM

Notice of Determination

Approving Agency
City of South Lake Tahoe
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No